# Baseline Climate Data Request: Keystone Behavioral Health

**From:** Sarah Mitchell, COO, Northwood Capital (prepared with Kith Consulting)
**To:** Jennifer Martinez (COO) and William Park (CFO)
**Issue date:** Monday, September 28, 2026 (planned)
**Edition:** Portfolio edition: Kith Climate cohort case, fictional client. The issue timetable is as planned in September 2026.
**Status:** As prepared for issue, September 2026

---

## Why This Matters

This is Keystone's first emissions baseline. Northwood will use it in Keystone's board materials, and it is the starting point for the energy and site-selection questions raised in your questionnaire. Your submission noted it was prepared without CFO review and offered corrections; this request is the opportunity for that review.

## What We Found in Your FY 2025 Submissions

We compared your carbon collection template with your climate questionnaire, figure by figure.

- The carbon template totals 1,312,000 kWh of electricity and 114,800 therms of gas. The questionnaire reports about 1,494,000 kWh and 120,400 therms: 12.2% and 4.7% higher.
- Six clinics carry an identical square-footage estimate (33,000 kWh each) in place of utility data.
- Trenton and Hagerstown opened in 2025 and are partial-year; Hagerstown has no data yet.
- The template includes Richmond VA with FY 2025 utility figures (76,000 kWh and 4,200 therms); your FY 2026 budget lists Richmond as a clinic opening in Q3 2026.

## What You Have Already Provided

These are not requested again:

- Electricity and gas for 21 locations, with the source for each.
- Confirmation that Keystone has no fleet vehicles or on-site fuel use.
- Weather-related closures in 2025 and their effect on sessions.

## What We Need

### Tier 1: needed to build your FY 2025 baseline (by Monday, October 5, 2026)

Without these, part of your FY 2025 baseline would rest on figures that currently conflict or are missing.

| Ref | What we need | What will satisfy it |
|---|---|---|
| KBH-1 | Which FY 2025 electricity and gas totals are correct (the template is 12.2% below the questionnaire on electricity), with CFO review | CFO-reviewed corrected template or confirmation |
| KBH-6 | Confirm whether the Richmond VA clinic operated in FY 2025 and where its figures (76,000 kWh and 4,200 therms) come from. Your FY 2026 budget lists Richmond as a clinic opening in Q3 2026 | The opening date and the utility account or statement behind the FY 2025 figures, or a corrected template row |

### Tier 2: confirms figures we will use provisionally (by Monday, October 12, 2026)

We will build your baseline on your submitted figures in the meantime and mark the affected items as provisional.

| Ref | What we need | What will satisfy it |
|---|---|---|
| KBH-2 | Utility or landlord statements for the six clinics currently carrying square-footage estimates | Landlord statements |
| KBH-3 | Opening dates and any consumption data for Trenton and Hagerstown | Lease start dates; first bills |

### Tier 3: needed for later work in this engagement (by Monday, October 12, 2026)

These inform the materiality, climate risk and disclosure work later in the engagement. Partial answers are welcome.

| Ref | What we need | What will satisfy it |
|---|---|---|
| KBH-4 | In-home therapist mileage for FY 2025, if tracked | Mileage reimbursement extract |
| KBH-5 | Street addresses for all clinics | Address list |

## How We Will Use It

- Your data is used for your company's baseline and Northwood's reporting only. It is not shared with other portfolio companies.
- Where an item hasn't arrived by the time the baseline is built, we use your submitted figures, mark them as provisional, and note what was assumed.
- If a document isn't available in the form described, send what you have and tell us what it covers. A partial answer by the date is more useful than a complete one later.

## How to Respond

Reply to Sarah Mitchell, quoting the reference (for example, KBH-1) against each item. Files can be sent in any format. Questions on any item can go to Daniel Vetsko at Kith Consulting, who is preparing the baseline.

Portfolio edition — Kith Climate cohort case, fictional client