# Baseline Climate Data Request: Harvest Ridge Foods

**From:** Sarah Mitchell, COO, Northwood Capital (prepared with Kith Consulting)
**To:** Thomas Nguyen (CFO)
**Issue date:** Monday, September 28, 2026 (planned)
**Edition:** Portfolio edition: Kith Climate cohort case, fictional client. The issue timetable is as planned in September 2026.
**Status:** As prepared for issue, September 2026

---

## Why This Matters

Three of your top ten customers, about $34.0M of combined revenue, now require Scope 3 supplier emissions data as a condition of 2027 contract renewal, and your strategic plan expects that to spread. Those customers will need Harvest Ridge's own footprint first, and it has to be right the first time: a baseline built on the wrong figures would have to be restated in front of them.

## What We Found in Your FY 2025 Submissions

We compared your carbon collection template with your climate questionnaire, figure by figure.

- Harvest Ridge submitted FY 2025 energy data twice, in the carbon template and the climate questionnaire, and the two disagree on every total: electricity -14.6%, gas -18.7%, on-site diesel +88.2%, propane -35.5%, fleet diesel -62.2% and fleet gasoline +9.1%.
- The questionnaire states its figures are April to December after the acquisition, annualized. The template doesn't state a period.
- Three template rows (Murfreesboro, Bowling Green, Chattanooga) have an extra field, which pushes the source label and notes out of position.
- The template has no field for R-404A or R-134a, so the refrigerant systems described in your questionnaire aren't captured.

## What You Have Already Provided

These are not requested again:

- Your supplier file (20 suppliers). We are asking only for sourcing evidence behind it, not a new supplier-spend submission.
- Refrigerant system descriptions and the June 2025 Nashville leak repair, from the questionnaire.
- Documentation of the 2025 water-pressure events at Bowling Green, in narrative form.

## What We Need

### Tier 1: needed to build your FY 2025 baseline (by Monday, October 5, 2026)

Without these, part of your FY 2025 baseline would rest on figures that currently conflict or are missing.

| Ref | What we need | What will satisfy it |
|---|---|---|
| HRF-1 | Corrected FY 2025 rows for Murfreesboro, Bowling Green and Chattanooga, and one stated period basis (12-month actual, or April to December annualized), replacing both earlier versions | Corrected carbon template |

### Tier 2: confirms figures we will use provisionally (by Monday, October 12, 2026)

We will build your baseline on your submitted figures in the meantime and mark the affected items as provisional.

| Ref | What we need | What will satisfy it |
|---|---|---|
| HRF-8 | January to March 2025 pre-close figures, if the prior owner's records allow | Prior-owner utility statements, or a short note saying they aren't available |
| HRF-2 | Fuel records backing the resubmitted fleet diesel and gasoline | Fuel-card statements or fuel invoices |
| HRF-3 | Refrigerant systems by facility (R-404A, R-134a, R-410A): system charges and 2025 recharge records | HVAC and refrigeration service records |

### Tier 3: needed for later work in this engagement (by Monday, October 12, 2026)

These inform the materiality, climate risk and disclosure work later in the engagement. Partial answers are welcome.

| Ref | What we need | What will satisfy it |
|---|---|---|
| HRF-4 | Sourcing evidence behind the existing supplier file (20 suppliers) | Supplier contracts, origin documentation, any supplier emissions data |
| HRF-5 | Business travel logs for FY 2025 | Travel booking or expense report extract |
| HRF-6 | Records of the 2025 water-pressure events at Bowling Green | Incident log or utility correspondence |
| HRF-7 | Street addresses for all facilities | Address list |

## How We Will Use It

- Your data is used for your company's baseline and Northwood's reporting only. It is not shared with other portfolio companies.
- Where an item hasn't arrived by the time the baseline is built, we use your submitted figures, mark them as provisional, and note what was assumed.
- If a document isn't available in the form described, send what you have and tell us what it covers. A partial answer by the date is more useful than a complete one later.

## How to Respond

Reply to Sarah Mitchell, quoting the reference (for example, HRF-1) against each item. Files can be sent in any format. Questions on any item can go to Daniel Vetsko at Kith Consulting, who is preparing the baseline.